An oil & gas customer experienced rapid operational growth and increasing volumes of environmentally sensitive brine, necessitating secure storage and evaporation. Unclear total storage requirements resulted in planning uncertainty.
An existing dam provided limited evaporation area and posed substantial regulatory and compliance hurdles. Constructing an additional dam would have required significant financial outlay, extended approvals, and complex environmental assessments.
As with most dams, oversizing is often used to mitigate future risk, further increasing costs and reducing operational flexibility. Since the brine could not be released to the environment, passive evaporation was critical while maintaining containment integrity.
Solution
Concept Tanks proposed a modular brine evaporation system, allowing capacity to scale with operational demands. Fast installation enabled just-in-time procurement, reducing upfront CAPEX and eliminating unnecessary oversizing.
The system required minimal earthworks and simplified approvals, supporting rapid deployment and earlier revenue recognition. Over four years, the team installed multiple tanks, each with double-lined containment using EnviroLiner and an integrated leak detection system.
The modular configuration enabled straightforward construction, while minimalist foundations will streamline future site remediation. The latest phase introduced a 78ML tank, further increasing flexibility and capacity.
Outcome
Five of the Concept Tank™ are now operational, delivering higher evaporation rates than conventional dams. The customer continues to highlight the solution’s scalability, cost-efficiency, and responsiveness to evolving project requirements while minimising total expenditure. Concept Tanks have since been deployed at multiple sites for this customer across Australia.