FLEXIBLE ENGINEERED FLUID STORAGE

The Concept AST™

0.6 ML–14.5 ML per system | No concrete foundations | Installed in 1–6 days

The Concept AST™ (Above-ground Steel Tank) is designed for short- to medium-term fluid storage. Prefabricated steel panels bolt together on an earthen pad, and the system is lined with a multi-layer geomembrane and commissioned within 1 to 6 days. At project end, it demobilises and redeploys with minimal site rehabilitation.
The Concept AST™ delivers engineered containment across oil and gas, waste, mining, industrial and data centre sites, without committing capital to permanent infrastructure.

Built for speed and flexibility

Prefabricated steel panels are delivered to site and bolted together using a telehandler. Construction is typically complete within 1 to 6 days of pad preparation, depending on system size, with no concrete, piling or long lead times.

A dual-geomembrane liner is standard, with a single liner available on request, installed and tested by the Concept Tanks liner team under its quality assurance (QA) regime. The earthen pad replaces a concrete slab, reducing both site preparation and end-of-life remediation.

The same system can be demobilised and reinstalled at the next site, suiting phased projects and changing storage demand

See also: Adaptability ↗

P CAST 01
P CAST 02

Where the Concept AST™ fits

Not every project justifies permanent infrastructure. Earthen dams, excavated ponds and concrete reservoirs require extended approvals, significant capital and a fixed footprint before any storage is available. For temporary or uncertain requirements, that means long lead times and a remediation liability at project end.

The Concept AST™ is available to buy, rent, or rent with a buy-out option.

Containment Certainty: end-to-end liner control and Leak Detection System

In-ground liners are difficult and costly to replace in situ. Above-ground installation makes relining a planned activity for the Concept Tanks liner crew, and keeps the system accessible for clean-outs and desludging.

Concept Tanks designs, fabricates, installs and QA-tests every liner in-house, with no third-party installers. The full liner surface is spark-tested on every installation, seam samples are taken for destructive testing, and repairs are validated on calibrated in-house equipment.

The dual-liner configuration enables the Leak Detection System (LDS), which monitors the interstitial space between the primary and secondary liners. A primary liner breach is identified before fluid reaches the ground.

P CAST 03

Fluids and Application

The Concept AST™ stores regulated and industrial liquids across five major sectors:

Potable Water

Remote sites, camps and temporary supply

Wastewater

Buffering ahead of treatment or disposal

Leachate

Interim and wet-weather storage

Emergency Storage

Response to wet-weather events and infrastructure failure

Data Centre Water

Construction and commissioning water, temporary fire water and contingency cooling water supply

Best for

01 1

Rapid installation is required.

large water storage tanks from 1 ML– 78 ML per system, multi-tank scaling to any project requirement

02

Tight Timelines

1–7 weeks from site-ready

03

Regulated Fluid Storage

leachate, produced water, brine, process fluids, raw water

04

Constrained Sites

High groundwater, limited excavation access, proximity to waterways.

05

Uncertain Project Timelines

fully relocatable, no stranded asset risk

06

High Compliance Exposure

dual liner system with end-to-end control, integrated leak detection system

The Concept Range

Concept AST™ Concept Tank™  Concept Utility Tank™
Best for Short- to medium-term, emergency and rental storage  Large, regulated storage that may grow, shrink or move  Permanent, high-capacity storage on a tight footprint 
Capacity per system  0.6 ML–14.5 ML  1 ML–78 ML (200 ML+ multi-tank)  12 ML–70ML
Structure  Bolted steel panels  Precast concrete panels on steel posts  Lined precast concrete panels 
Construction time (after site prep)  1–6 days  1–7 weeks  3–4 months 
Structure design life  Up to 5 years, on condition  25-years+ Up to 100 years
Foundation  Earthen pad, ≥100kPa  Earthen pad Concrete ring beam 
Specific gravity  Up to 1.2 (higher on request)  Up to 1.2 (higher on request) Up to 1.2 (higher on request)
Relocatable Yes Yes No
Leak Detection System  Standard  Standard  Standard 
Solution pathway  Rapid Deployment, Adaptability  Adaptability, Rapid Deployment, Compliance Assurance  Compliance Assurance 

The Concept Range

Capacity
Diameter
Wall height
0.6 ML 21 m  1.80 m 
1.1 ML  28 m  1.80 m 
1.4 ML  24.4 m  3.00 m 
4.6 ML  42 m  3.450 m 
5.2 ML  42 m  3.670 m 
6.1 ML  45.50 m  3.670 m 
7.1 ML  49 m  3.670 m 
9.8 ML  70 m  2.450 m 
14.5 ML  70 m  3.670 m 

Technical Specification

Capacity0.6 ML–14.5 ML per system (21–70m diameter)
StructurePrefabricated bolted steel panels
LinerMulti-layer geomembrane liner with conductive geotextile and Leak Detection System as standard; single liner available on request
Structure design lifeUp to 5 years
Liner design life20 years (conditional pro rata manufacturer's warranty)
Build time1–6 days depending on asset size (after site preparation)
Construction methodPrefabricated steel panels bolted together on site; liner installed and QA tested by Concept Tanks’ in-house team; telehandler required on site; trailer-deployable and runs off-grid
Specific gravityUp to 1.2 (higher on request)
FoundationHardened earthen pad with inverted conical base.
Wind loadRegional wind speed compliant
Design standardsSee Compliance Assurance ↗
Liner QA and testingAir lance seam testing; destructive seam sampling; vacuum box testing of extrusion welds; full-surface spark testing. Hydrostatic testing available on request
RelocatableYes. Demobilisation takes 1-3 days

Configuration Option

  • Leak Detection SystemSTANDARD
  • Custom PipeworkSTANDARD
  • BallastSTANDARD
  • SCADA System/Remote MonitoringADD - ON
  • Engineered Floating CoverADD - ON
  • Viewing PlatformADD - ON
  • Overflow WeirADD - ON
  • Bird NettingADD - ON
  • Anti-climb ProtectionADD - ON

Proven in the field

Concept Tanks has supplied fluid storage to Australia's energy sector for over 17 years. That includes nearly 200 brine systems and 30+ brine concentrate systems on CSG and onshore oil and gas sites. We manufacture in Australia and install with our own crews. That means faster mobilisation and no handover between contractors. 

Concept AST™ in an urban industrial environment.

Rapid Remediation Fluid Storage

Remediation runs on a simple sequence. Treating contaminated earth includes treating contaminated groundwater. You can’t start treating contaminated groundwater without suitable storage. Storage sits on the critical path of remediation projects where downstream...

read more
Concept AST™ on a dirt pad at a Fracturing site.

Rethinking Frac Fluid Storage In Australia

Frac water management is logistically complex. Remote sites, variable conditions, and strict project schedules mean any delay in water delivery can increase standby costs and disrupt operations. A recent project required 14.5ML of temporary storage capacity for a...

read more
Two Concept Tank™ on an Oil and Gas site in Queensland

Dynamic Brine Services

Our customer in the Oil & Gas industry required secure on-site water storage system for contaminated flowback water to avoid the chance of discharge of contaminated water, which was essential in managing costs in relation to their gas production and frack pilot...

read more

Frequently asked
questions

Common questions about the Concept Tank, Utility Tank, and Concept AST range. 

What sizes does the Concept AST™ come in?

Standard sizes run from 0.6ML to 14.5ML per system: 0.6, 1.1, 1.4, 4.6, 5.2, 6.1, 7.1, 9.8, and 14.5ML.

How long does a Concept AST™ take to install?

Construction is typically complete within 1–6 days of civil pad preparation, depending on system size. Systems up to 4.6 ML can be holding fluid in under 2 days. 

Does the Concept AST™ need concrete foundations?

No. The system sits on a hardened earthen pad with a bearing capacity of at least 100 kPa. No concrete, no piling. 

Can the Concept AST™ be relocated?

Yes. When the project ends, the system demobilises and redeploys at the next site with minimal site rehabilitation. 

Can I rent a Concept AST™ rather than buy one?

Yes. The Concept AST™ is available to buy, rent, or rent with a buy-out option. Renting suits short-term, emergency and stop-gap storage: when the job ends, the system demobilises and goes back. See Ways We Work for every delivery and commercial option. 

What fluids can the Concept AST™ store?

Potable water, wastewater, leachate and emergency water, with a specific gravity of 1.0–1.2. We can accommodate higher SG on request. 

Discuss your requirements

Concept AST™ delivers fully engineered steel water storage tanks from 0.6 ML to 14.5 ML. Installed in 1–6 days on a hardened earth pad with no concrete foundations. Demobilise, relocate, and redeploy as your project evolves across oil and gas, waste, mining, and industrial sites. 

If you are evaluating flexible fluid storage for your site, contact us to see whether it is technically suitable for a Concept AST™. Solving tomorrow’s problems, today.