Future-Proofing Landfill Fluid Storage

by Koby Tunney | Nov 10, 2026

Two Concept Tanks™ at a council landfill surrounded by trees.
PROJECT

1.3ML Concept Tank™
2.6ML Concept Tank™
Local Government Landfill

LOCATION

New South Wales

APPLICATION

Leachate Storage

TIMEFRAME

19 Days

Summary

<p>A New South Wales council was incurring high operational costs by carting leachate offsite from its landfill facility while simultaneously facing pressure from the state EPA to achieve compliance or face penalties.</p>
<p>Concept Tanks delivered a two-tank leachate storage solution equipped with Engineered Floating Covers (EFCs) and a double-lined system for leak detection, allowing the council to manage leachate on-site and meet its regulatory obligations.</p>

This Council incurred substantial ongoing costs to transport leachate offsite for disposal, draining the operational budget with no long-term infrastructure value. Compounding this, the site faced active environmental compliance risks, with the state EPA mandating action. Failure to respond would have presented potential financial penalties and lasting reputational consequences for Council.

Beyond the immediate compliance pressure, Council faced a more complex design challenge: a permanent long-term leachate processing plant was already on the horizon, meaning any interim solution risked becoming a stranded asset. The critical requirement was a storage system that could meet EPA standards now while remaining fully adaptable for future use, so the council wouldn't have to start from scratch when the permanent plant was ready.

Solutions

Concept Tanks designed both tanks with future flexibility at the core. Each tank can be deconstructed, relocated, and reconfigured into larger (or smaller) units as the Council's permanent long-term plant requirements evolve. All are manufactured with a tapered profile that works for the current tank dimensions while remaining compatible with the future consolidated configuration. The double-lined system provides continuous leak detection, directly satisfying the EPA's containment requirements.

Before breaking ground, Concept Tanks' Engineering team coordinated closely with Council and the System Integrator to resolve panel penetration design and under-float inlet/outlet piping interfaces early, avoiding costly mid-build rework.

On-site, significant wet weather tested the team throughout the project.

When limited site access became a constraint, the team switched the prefabricated liner supply from large single-piece units to a bucket-style approach, keeping construction moving safely. The Concept field team delivered the project on time, on budget and without safety, quality or environmental incidents.

Outcomes

  • Achieved full EPA compliance, eliminating enforcement risk and environmental liabilities.
  • Unconstrained Council’s operations
  • Cut recurring transport and disposal costs, delivering immediate operational savings for the council.
  • Reduced exposure to weather-related delays and logistical risks.
  • Delivered solution on schedule with zero safety incidents.
  • Designed tanks for future relocation and reconfiguration, ensuring long-term value and avoiding stranded assets.

With relocatable and reconfigurable tanks now in place, Council can seamlessly transition to its long-term processing plan, avoid unnecessary spend, and invest capital wisely. By exceeding compliance standards and prioritising future adaptability, Concept delivered a solution that maximises value for both site operations and procurement planning.